Elbphilharmonie Hamburg

Clarity before warranty deadlines.

The Elbphilharmonie was already in operation as key warranty periods approached their end. Working for SPIE as an independent construction expert and Senior Advisor, Frank-Michael Adam investigated technical risks, from fire-stopping systems and damage to hotel showers to the Plaza and electrical power quality.

Elbphilharmonie Hamburg
Architectural photograph · Project contextViola sonans / Wikimedia Commons · CC BY-SA 4.0
Cropped view
What this means for your decision

Executive Project Review

Clear priorities for addressing technical problems and deciding what to do next.

01

The situation

Concert spaces, the Plaza, hotel, restaurants, apartments and extensive technical systems make the Elbphilharmonie an unusually complex building. It had already been operating for several years when the assignment began. Before major warranty periods expired, SPIE needed an independent assessment of technical problems: their causes, their implications for safety and operations, and the measures required.

02

Contribution to the project

From September 2020 to March 2021, Frank-Michael Adam worked for SPIE as an independent construction expert and Senior Advisor. Systematic inspections and a building-wide review led to more detailed investigations of individual technical issues. Alongside his own investigations, he reviewed existing technical records and independently assessed earlier expert findings.

Key areas of the assignment

  • Examined fire-stopping systems and as-built records for technical and safety-related deficiencies.
  • Analysed the causes of damage to 93 hotel showers and recommended remedial measures taking ongoing operations into account.
  • Provided an independent second assessment of damage to the Plaza.
  • Independently reviewed and compared existing expert opinions on electrical power quality and assessed their implications for the next decision.
03

The outcome

SPIE received an independent technical basis for assessing the identified defects and risks before key warranty periods expired, and for prioritising the next steps. For fire-stopping systems, the 93 hotel showers, the Plaza and electrical power quality, the assessment examined causes, implications for safety and operations, and available options. This supported decisions on remedial work and warranty matters while taking the building’s ongoing operation into account.

Which decision do you need to make?

Briefly describe your project, the decision ahead and your timeframe. In an initial conversation, we will clarify the question, the information available and whether independent advice is the right next step.

Write to Frank-Michael Adam

LinkedIn profile

Prof. em. Dr.-Ing. habil.
Frank-Michael Adam

Frankfurt am Main, Germany · International assignments

German · English · Russian

Telephone+49 151 5624 8893